Stability for the grid, heat for the city
The project brings together, on the CET-Nord site, a battery energy storage system of 70 MW / 140 MWh and a 25 MW cogeneration plant with gas-fired internal combustion engines, connected at 110 kV in the existing CET-Nord substation.
A strategic project. It is included in the list of strategic investment projects and is critical for energy security.
A prepared site. The 110 kV connection, the gas pipeline from the transmission network, the environmental approval and the technical concept are in place.
What it brings to the system. Stability for the transmission grid and heat for district heating in Bălți.